| Cab Windows |
| 05/01/2026 |
| |
 |
| |
We have had a trial fit of the cab windows today. A little more easing is required. At the moment the cab is assembled with temporary bolts. Once we are happy with how everything fits together, the roof will be dismantled and sent off for blast cleaning. |
| |
|
| Cab Work Continues |
| 12/01/2026 |
| |
 |
| |
Jim was at work today cleaning up the leading edge of the cab roof. This will help us get the spectacle plates at the front of the cab to fit.On the left, Geoff can be seen measuring brake hanger bolt holes. We will need to order heavy drive, fitted bolts here. |
| |
|