Build Diary entries for February 2026
Here are the diary entries for this month. You can use the forward and backward links to see the next or previous months. Most photos taken before 2018 are small size. From 2018 onwards, most photos you see below will have a link to a full size image by clicking on the photo.
| Sandboxes and Filler Pipes |
| 02/02/2026 |
| |
 |
| |
CTL Seal are now known as Diamond Engineering. Today a couple of jobs related to the sandboxes were completed. On the sandboxes, the holding down brackets (or feet) have been fully welded in place. The sandbox filler pipes (on the left) have now been welded up. Diamond Engineering have also welded on the pads that are on the sides of the pipes. These provide a base for pipe clamps. |
| |
|